Builder guide

Edmonton infill rollback: what builders need to know

Last updated November 6, 2026. Draft amendments have not been released yet.

The short version

  • Alberta has ordered Edmonton to amend its zoning rules for the RS (Small Scale Residential) Zone by January 22, 2027.
  • Uses, density and height go back to rules comparable to the old Zoning Bylaw 12800, and on-site parking minimums return.
  • Approved development permits can proceed. Pending applications are decided under whichever bylaw is in force on the day of the decision.

What the order says

The Order in Council of October 22, 2026 gives the City three months to amend Zoning Bylaw 20001. The changes are limited to the RS Zone, in the areas of uses, height, density and parking.

  • Uses, density and height: the same as comparable residential lots under repealed Zoning Bylaw 12800, as of December 31, 2023.
  • On-site parking: the same as comparable lots under Bylaw 12800 as it read on July 1, 2020. Edmonton removed minimum parking requirements citywide the next day.

The RS Zone primarily regulates residential areas inside the Anthony Henday, and covers about 49% of the city's legal parcels. Because of the short timeline, the City says there will be no public input on these 90-day changes.

Key dates

DateWhat happens
Oct 22, 2026Province issues the Order in Council directing the City to amend Zoning Bylaw 20001.
Nov 8, 2026, 11:59 PMCity's date for complete RS Zone applications expected to get a decision before the amendment. Not a guarantee.
Mid-November 2026Draft amendments expected to be posted online.
Dec 2, 2026, 11:59 PMSame expectation, for complete applications using the City's Standardized Designs. Not a guarantee.
Dec 10 to 15, 2026Anticipated timeline for reports and the bylaw to be finalized.
Dec 28, 2026 and Jan 4, 2027Anticipated advertising dates.
Jan 22, 2027Public hearing required on or before this date.

The mid-November date comes from City administration, as reported by Taproot. The other dates are from the City's Zoning Bylaw Update page.

If your application is in progress

Until the bylaw is amended, the City must keep accepting and processing development permit applications under the current rules. But applications are decided under the bylaw in effect on the date of the decision, so if the rules change before your decision, the new rules apply.

The November 8 and December 2 dates are based on typical processing times. The City says they do not account for a sharp increase in volume and do not guarantee a decision before the change.

If an application is still pending when the amendments take effect, a Development Approvals representative will contact the applicant to ask whether they want to update it to meet the new rules or withdraw it. Applicants only need to contact their development planner if asked to, or if they plan to modify their plans. The City says status update requests will not be returned.

If your permit is already approved

Approved development permits, including projects under construction, can proceed as planned. But a permit does not last forever. You must obtain a valid building permit and start construction while it is valid:

  • Single, semi-detached and backyard houses: one year.
  • Larger developments such as row housing: two years.

What is not affected

  • Rezonings: applications proceed as usual, and previously approved rezonings remain valid.
  • Curbside parking: the order covers parking on private property in the RS Zone, not off-site parking programs.
  • Other application types: these are expected to follow current service levels.

Other rules to keep in mind

  • Maximum height in the RS Zone dropped from 10.5 m to 9.5 m, in effect August 1, 2026.
  • Landscape securities expand to small-scale residential development on January 1, 2027. See our landscape deposit guide.
  • A second City project, of 18 months or less, will align zoning with the Province's infill policy statement. It will include public engagement.

What we don't know yet

  • The exact wording. The City says parking specifications will be available when the draft amendments are shared.
  • How the Province's wording will be applied. City Council voted to have administration and the mayor present their interpretation to Alberta's Ministry of Municipal Affairs and ask for clarification.
  • The effect on review times. The City says specific service level impacts are not known.

Sources

This guide is general information, not legal or planning advice. Rules and dates may change, so confirm the current requirements with the City of Edmonton for your site.